Works continue at 13.80MW Windfarm

Murnane & O’Shea Ltd have completed all civil enabling works and the installation of the Section 5′s for the turbine bases.  All turbines are now fully commissioned with a view to project completion by June 2015, which is two months ahead of the construction programme schedule.

 